See all service disruptions

Engineering work details

Starts Sunday 16 February 2025 to Saturday 17 May 2025

If you would like to follow this incident on X, please use

Train operators affected

Route(s) affected

Between Wemyss Bay / Gourock / Ayr and Glasgow Central

Description

Engineering work is taking place on Platform 1 at Hillington West station, closing the platform for 13 weeks (project background information is available below).

Due to this, Eastbound trains (towards Glasgow Central) will not call at Hillington West. Westbound services (towards Wemyss Bay / Gourock / Ayr) are not affected by this and will run as normal.

If you are travelling to / from Hillington West you should instead travel to / from Hillington East if possible. Hillington East is a short distance from Hillington West.

Check before you travel:

You can plan your journey using the National Rail Enquiries Journey Planner

Background information on this project:

Network Rail will be delivering nearly £3m of upgrades in platform works at Hillington West station. The investment will not only improve safety and reliability of the railway but will provide modern, safer platforms and wider improvements to the station environment for passengers.

The project consists of two 13-week phases, the first phase being the renewal of platform 1. Once platform 1 is renewed it will reopen and teams will then spend 13 weeks renewing platform 2.