Completed major engineering work during the August Bank Holiday weekend, from Saturday 29 to Monday 31 August
Service alteration details
Incident reported: Friday 28 August 2026 at 10:38
Incident cleared: Tuesday 01 September 2026 at 09:56
If you would like to follow this incident on X, please useAugustRailWorks
Last updated
Tuesday 01 September 2026 at 09:56
Train operators affected
Route(s) affected
Various routes
Description
Planned essential engineering works and upgrades took place during the August (also known as Summer) bank holiday weekend as Network Rail worked to improve the railway - Network Rail carry out essential improvement and engineering work across the rail network during this time as fewer people usually travel by train.
The following works were completed as planned:
London Kings Cross: Starting at 22:00 on Saturday 29 August and finishing at 08:00 on Tuesday 1 September, major East Coast Digital Programme (ECDP) engineering work took place between London Kings Cross and Peterborough.
London Bridge - Tulse Hill: From Saturday 29 to Monday 31 August, track renewal work closed the south of London lines between London Bridge and Tulse Hill via Peckham Rye.
Other bank holiday weekend engineering work to have been completed was between Birmingham New Street - Coleshill Parkway, in the Leeds / York area, between London Charing Cross - Hayes (Kent), in the Guildford area and between Farnham - Alton.
The longer term engineering work in the Wrexham area has been completed.